Statement of Work Example: An Annotated SOW Section by Section

You have a statement of work to review or draft, and a blank page tells you nothing about the wording. One annotated SOW, section by section, and why each sentence is written the way it is.

A statement of work example shows how one project’s scope, deliverables, acceptance criteria, timeline and fees are written down under a parent agreement, so both sides know exactly what will be delivered and how it will be judged. The legal terms (liability, indemnities, IP, governing law) stay in the master service agreement, and the SOW carries only what is specific to the project.

This page walks through one annotated SOW section by section, explains each wording choice, and adds a short consulting variant. Every real SOW still needs its own review under its governing law.

What does a statement of work example look like?

A statement of work example is a short project document, signed under an MSA, that answers who does what, by when, to what standard, and for what price. Our example is a company engaging an IT services supplier to migrate HR records into a new system over 12 weeks.

A SOW answers the who, what, when, where, why and how of the work. The definition of a SOW and who approves it are covered in our statement of work guide, so this page stays on the wording.

In our implementations, a SOW is a child contract record under its parent MSA. The intake form requires the requester to pick an active MSA before the SOW can be created, and up to 10 supporting files carry over from the request into the draft.

What sections does a sample statement of work include?

A sample statement of work includes background, scope, deliverables, acceptance criteria, timeline, fees, assumptions, change control and an order of precedence clause. Boilerplate legal terms are left out because the MSA already holds them.

The table below is the annotated example. Each row gives the section, what our example SOW says, and why it is worded that way.

SOW section What the example says Why
Background “Customer is replacing its HR system and needs 4 years of employee records moved.” Gives reviewers the purpose, so ambiguous scope is read against the goal
Scope “Supplier shall migrate current and former employee records for the UK and US entities. Payroll history is out of scope.” Names the entities and states the exclusion in the same place
Deliverables “D1 data mapping document; D2 test migration; D3 production migration; D4 closure report.” Numbered deliverables can be accepted, paid and tracked one by one
Acceptance “Customer has 10 business days to accept or reject each deliverable in writing, with reasons.” Sets a review window and makes rejection specific
Timeline “D1 by week 3, D2 by week 7, D3 by week 11, D4 by week 12.” Dates tie to deliverables, so slippage is visible early
Fees “Fixed fee of $80,000, invoiced 25% on acceptance of each deliverable.” Payment follows accepted work
Assumptions “Customer provides a cleaned data extract by week 2 and a named HR contact.” Puts the customer’s dependencies on paper
Change control “Any change to scope, dates or fees requires a written change order signed by both parties.” Stops informal email changes from altering the deal
Precedence “This SOW is governed by the MSA dated 1 March 2026, which prevails in any conflict unless this SOW expressly overrides a named clause.” Keeps the legal terms in one place

The figures are illustrative. In our implementations, the SOW record holds only commercial and operational fields, such as dates, deliverables, contract value and key personnel, and we hid MSA-only fields like annual uplift because they cluttered the screen.

How is scope written in a statement of work example?

Scope in a statement of work example is written as a short statement of what is included, followed by what is excluded, in active voice with the supplier as the subject. Each sentence should name who acts, on what, and where.

The US federal rule sets a useful floor: every federal SOW must include a description of work, location, period of performance, deliverable schedule, applicable performance standards and any special requirements. Our example follows these habits, including active voice, because passive sentences create ambiguity:

  • Actor first. “Supplier shall migrate” names who is responsible. “Records will be migrated” leaves it open.
  • Countable objects. “Current and former employee records for the UK and US entities” can be checked. “All relevant data” cannot.
  • Exclusions in writing. “Payroll history is out of scope” heads off the most likely dispute before it starts.
  • Standards named. If the work must follow a data security policy or an industry standard, the scope names it.

How are deliverables and acceptance criteria written?

Deliverables are written as a numbered list of concrete outputs, each with a due date, and acceptance criteria are written as measurable conditions plus a review window. A deliverable without acceptance criteria gives neither side a clear point at which it is done.

Our example uses these rules for each deliverable:

  • One output per line. “D2 test migration” is one thing that can be accepted or rejected.
  • A measurable test. “Test migration reconciles 100% of record counts and passes the agreed sample checks” can be verified.
  • A review window. Ten business days to accept or reject, with written reasons for any rejection.
  • A cure step. A rejected deliverable is corrected and resubmitted, and the same window runs again.

Check that the acceptance wording matches any acceptance or cure provisions in the MSA, so the two documents do not set different clocks. In our implementations, deliverables and key dates become obligation records on the signed SOW, each with a named owner.

What does a consulting statement of work include?

A consulting statement of work includes the advisory objective, the outputs the consultant will produce, the named key personnel, the fee model, and how time or effort is reported. Advice is hard to measure, so outputs need firm definitions.

The consulting variant of our example changes four sections:

  • Objective. “Consultant shall assess the current HR data model and recommend a target design” frames advice as an output.
  • Outputs. A current-state assessment, a recommendations report and one review workshop, each with a date.
  • Key personnel. The named lead consultant, replaceable only with the customer’s written approval.
  • Fees. Hourly, fixed or capped, and a cap with monthly time reports gives finance predictable spend.

What is a good statement of work format?

A good statement of work format is a numbered Word document with the same section order every time, defined terms from the MSA, and party names, dates and values filled automatically. A fixed order lets reviewers find scope, fees and acceptance terms in seconds.

In our implementations, the SOW format is an editable Word template in a governed library. Generation fills 15 or more fields from the request, legal redlines in Word, and the final version goes to PDF for signature. One master template serves 5 languages.

A statement of work template is only a structure. The wording in each section still has to be written for the project.

How does the example SOW link to the MSA?

The example SOW links to the MSA through a governing-agreement clause that names the MSA by date and an order of precedence clause that says which document prevails in a conflict. In the system, the SOW record is linked to its parent MSA record so both show the relationship.

A loose SOW is costly, because research on contracting puts average value erosion at 8.6 percent of contract value, with the worst performers losing more than 20 percent, which is why the SOW and MSA must agree. How the two documents divide terms is covered in our MSA vs SOW guide. Whether a precedence clause works as intended depends on its wording and the governing law, so legal reviews it for every SOW.

In our implementations, SOW intake has a mandatory parent contract field, and choosing the MSA creates 2 relationship records, one on each side.

Conclusion

A statement of work example is most useful when you can see why each sentence is written the way it is. Name the actor, count the objects, state exclusions, tie each deliverable to a date and a test, and point the precedence clause at a dated MSA. Then link the SOW to its MSA in your contract lifecycle management system so the relationship survives after signature.

How Basla can help

Basla provides delivery teams for contract lifecycle management software implementation, covering business analysis, SOW and MSA template setup, parent-child contract linking, obligation tracking, testing, documentation, and post-go-live support. We deliver legal technology services through staff augmentation or a Basla-managed delivery unit, and we configure SOW intake so every new SOW starts linked to its MSA.

Frequently asked questions

Is there a standard statement of work template?

There is no single standard statement of work template, though most follow the same section order: background, scope, deliverables, acceptance, timeline, fees, assumptions and change control, as in the statement of work example above. In our implementations, SOW templates sit in a central library with version control, and dynamic fields handle regional differences.

How long should a statement of work be?

A statement of work should be as long as the scope needs and no longer. A single-deliverable SOW can fit on a few pages, while a multi-phase project with several deliverables runs longer. Legal terms already in the MSA should not be repeated, which keeps most SOWs short.

What is the difference between a SOW example for services and for software?

A services SOW example centers on tasks, people and deliverables, while a software SOW adds configuration, testing environments, data migration and acceptance testing. Software SOWs usually need firmer acceptance criteria, such as passing defined test cases.

Who writes the first draft of a SOW?

The business owner usually supplies the facts for the first draft, and legal or the contract manager turns them into the SOW. In our implementations, business users submit scope details and any supplier draft through the intake portal with up to 10 attachments, and the assigned legal manager generates or attaches the official draft.

Should pricing sit in the SOW or the MSA?

Project pricing should sit in the SOW, while payment terms and invoicing rules that apply to every project sit in the MSA. In our implementations, SOW records hold the total and annual contract value, so fees can change project by project without amending the MSA.

How do you handle changes to the example SOW after signing?

Changes to a signed SOW are handled through a written change order or amendment signed by both parties, following the change control section. In our implementations, an amend action marks the original SOW as being amended, the amendment goes through review, approval and signature, and the original record updates to amended once the change is active.


*This article is provided for general information only and does not constitute legal advice. Basla Solutions provides legal technology implementation and support services and does not practice law.*

Hassan
Hassan

Muhammad Hassan is a software engineer and Legal Technology Developer at Basla Solutions with expertise in full-stack MERN development, DevOps engineering, workflow automation, CLM implementations, eBilling implementations, and enterprise legal management systems. He is skilled in building scalable web applications and CI/CD pipelines, with a focus on writing clean, maintainable code and delivering production-ready digital solutions. As an author, Hassan regularly shares technical knowledge and engineering perspectives with the legal technology community. His articles focus on both the business and technology aspects of legal technology. He writes on topics such as requirements gathering, applying unique solutions to legal workflows, evaluating legal tech solutions, implementing specific solutions, scalable web application design, CI/CD automation, and AI workflow development.